calculation in ASCP when fore cast is loaded

How to calculate ASCP
---> Fore cast ---> 100
--> planned order ---> ?
---> planned order Demand-->?
---> Sales order -->25
---> on hand -->25
---> open work order -->10
---> safety Stock --> 5

pls give the calculation

You have not mentioned the lead time, time bucket & demand time fence. So lets assume all the data are for active bucket

---> Fore cast ---> 100
--> planned order ---> ?
---> planned order Demand-->?
---> Sales order -->25
---> on hand -->25
---> open work order -->10
---> safety Stock --> 5

planned order Demand = 25 if its with in demand time fence
= 100 if its out side demand time fence

Total on hand = 10 + 25 = 35

So if its with in DTF then planned order = 0
as 5 + 25 In fact you 'll get reschdule out exception message

if its out side DTF then planned order = 100 + 5 - 35 = 70

One proint I missed is the lot size

The planned order might be differnt if you are using any fixed lot

thank you its very clearly understandable

Can you pls eplain an Example with the lead time, time bucket & demand time fence