Req for OSP
I followed the steps for OSP but the requistion is not getting created...
what could be the problem
Possible Root Causes for the
Possible Root Causes for the OSP requisition not being generated include:
- There is no List Price defined for the OSP item in the Item Master.
- OSP Resource Charge type is not set as PO Move / PO Receipt.
- OSP item is not linked to the OSP resource.
- OSP resource is not linked to the OSP operation.
- There is no Location defined for the Department for which the OSP resource is linked.
- When the quantity involved for OSP is large. you see no requisitions being created for the quantity (Cause: Organization calender does not have a long period defined. This is an issue when the item has a large lead time and for WIP to schedule large OSP quantities according to their lead time may exceed the calender defined for the organization.)