Material Requirements Planning
The purpose of the planning process is to derive an MPS, DRP or MRP that meets schedule dates while maintaining inventory levels within your “material” policies. You can validate a material plan against available capacity using rough cut capacity planning (RCCP) or detailed capacity requirements planning (CRP).
Material requirements planning (MRP) calculates net requirements from gross requirements by evaluating:
- the master schedule
- bills of material
- scheduled receipts
- on–hand inventory balances
- lead times
- order modifiers
- discrete quantities, with due dates
- repetitive build rates, with first and last unit start dates.
safety stock
Safety stock also important that we use to calculate MRP. if we see the flow below that there are no safety stock atribut.